Thomas P. Smith WRF Improvements – Phase 2 BNR Upgrades

  • Value: $18,700,000
  • Started: 2011
  • Completed: 2015
  • Location: City of Tallahassee, FL
  • Owner: City of Tallahassee
  • Engineer: Hazen and Sawyer

Project Description

BNR upgrades at a 26MGD WWTP. Upgrades include complete changeover of BNR mechanical equipment including new baffle walls, mixers and diffused air systems for all six BNR basins. Also upgrades to six clarifiers. Related upgrades to yard piping and chemical buildings and chemical piping.